Where Paradise Still Has Overhead Power, and When It Goes Underground

"What was explained to me originally was that once we were undergrounded, we should not have PSPSs at all," Paradise Mayor Steve Crowder told NSPR on October 13, 2026, after PG&E put parts of town on its shutoff watch list. He said the town had not had a public safety power shutoff since 2020.

PG&E spokesperson Paul Moreno gave NSPR the other half of the picture. "We have been undergrounding power lines throughout the community. We are not yet finished, so there will be customers within Paradise that will likely be impacted," he said. The watch named the south and east edges of Paradise, along with parts of Magalia, Concow and Berry Creek. The shutoff went ahead. At about 2:40 p.m. on October 16, outage data cited by KRCR showed 1,269 Paradise customers without power from the shutoffs. By October 17, PG&E reported that virtually all customers who had been shut off were back on.

For anyone comparing homes or lots on the Ridge this winter, "Paradise is underground" depends on the address and the date. The corridors PG&E is finishing last are the same corridors where the Town of Paradise has its last major road projects waiting. A house on one of those streets comes with utility and road construction scheduled into 2028.

The Percentage and the Miles Left

PG&E told KRCR on November 3, 2026 that more than 95% of Paradise has been undergrounded, under a pledge the company made in 2019 covering Paradise and portions of Magalia.

PG&E's mileage forecast shows how much remains. On its October 2026 undergrounding map, the City of Paradise has about 7 miles in the 2026 completed-or-forecast category, 10 miles forecast for 2027 and 3 miles for 2028. Countywide, PG&E's Butte County undergrounding page showed 9 of the 15 miles forecast for 2026 completed as of November 2, 2026, with 37 miles forecast for 2027 and 12 for 2028. PG&E says those years mark when projects are expected to be energized, and schedules can shift with access, weather and permitting.

Some lines will stay overhead permanently. Moreno told KRCR that the high-voltage transmission lines feeding Paradise's substation will remain above ground, and that undergrounding the distribution lines will not remove every possible reason for a shutoff. Once the work is complete, shutoffs in town should be less common. They are still possible.

Pentz Road, Bille to Arrowhead

Pentz Road is under construction now. PG&E started work on November 2, 2026 on the stretch between Bille Road and Arrowhead Drive and expects to continue through July 2027. The Enterprise-Record photographed equipment staged at a temporary laydown yard on Pentz near Bille that first Monday.

According to KRCR's report on the project, the three sections of Pentz are at different stages:

Section of Pentz Road Underground conduit Customers switched to underground service Street restored
Bille Road to Skyway Built Scheduled for November 2026 Not stated
Bille Road to Arrowhead Drive Under construction, Nov. 2026 to July 2027 2027, then poles removed or shortened Final restoration expected by end of 2027, weather permitting
South of Arrowhead Drive Complete Not stated Not stated

Day work runs Monday through Friday, 6 a.m. to 6 p.m., with one lane closed and a pilot car guiding traffic. Night work begins November 30 and continues through July on Monday nights through Saturday mornings, 6 p.m. to 6 a.m. During those hours, drivers are detoured from Bille Road to Pearson Road by way of Sawmill Road. PG&E is also moving natural gas lines in some areas to make room for the Town's planned storm drain and roadway improvements.

The schedule matters for anyone house hunting. A home on the Bille-to-Arrowhead stretch may still be on overhead service for most of 2027. For the first eight months of ownership, its street will have lane closures in the day and a night detour five nights a week. A home on Pentz between Bille and Skyway is scheduled to switch to underground service this month.

Neal Road Is Last, and the Town's Projects Run on the Same Clock

Moreno told KRCR that the last undergrounding project in Paradise will involve Neal Road, with completion in 2028. A June 2026 California Transportation Commission staff memo explains why Neal goes last. A high-priority gas transmission line runs along the Neal Road alignment, which makes undergrounding there more complicated, and at the time of the memo PG&E expected to finish that stretch in fall 2027.

The memo also lists the Town's own projects on both corridors, each extended because of utility coordination and right-of-way work:

  • Go Paradise: Pentz Student Pathway. The construction phase is listed at $19,911,000. The Town reported delays from coordinating with PG&E, which is installing a joint trench along the alignment ahead of the Town's work. The Town requested a 20-month extension, to February 29, 2028.
  • Go Paradise: Neal Gateway Project. The construction phase is listed at $10,519,000. It was also extended to February 29, 2028, and right-of-way work includes owner impact exhibits and title reports for affected parcels.

Paradise has finished most of its road rebuild, which we covered in our post on the town's last seven miles of roadwork. On Pentz, the Town's pathway is sequenced behind PG&E's joint trench, and on Neal, the Town's gateway project shares a corridor with PG&E's most complicated remaining work. For a buyer, overhead power and a street with more construction to come both point to the same corridors, and the timelines for both run into 2028.

Checking a Specific Address

The south and east edges of town, Pentz Road and Neal Road are the areas the reporting names. Below that level, the most useful tool is PG&E's own. The Butte County undergrounding page has a progress map where you can search an address and see the wildfire-safety work and project status for that location. PG&E notes that schedules and project locations can change. During a shutoff event, PG&E's address lookup for shutoff updates shows whether a specific address is in scope.

Two questions for a seller fill in what the maps leave out. First, did the house lose power during the October 2026 event? Second, is there a pole still feeding the house, or has PG&E already switched it to underground service? The first answer tells you about this fall. The second tells you whether the switchover is still ahead.

For a vacant lot, the question becomes how long a new house waits for power. PG&E's published new-service timeline lists 66 calendar days from application to approval and phase averages that add up to 182 calendar days. At least 5% of projects take up to 357 days, and permit time from agencies is not included. Those are PG&E's systemwide averages, not figures specific to Paradise. On Pentz between Bille and Arrowhead, PG&E's own corridor schedule puts customer switchovers in 2027, so a build there runs on two calendars, the builder's and the corridor's. Our post on Paradise's sewer service area covers the other utility a lot buyer should check before writing an offer.

On Pentz and Neal, the switchover dates are published, and they belong in your timeline as much as the closing date does.

If you're weighing a home or lot on Pentz, Neal or anywhere else on the Ridge and want to know where that street stands before you write an offer, Speicher Real Estate will check the address against PG&E's schedule with you. Browse current Paradise listings, or if you own on one of these corridors and are thinking about timing a sale around the switchover, start with a free home valuation.